ISO 14001
   

 

            STATUS  OF IMPLEMENTATION OF ISO?1400:

Kota Workshop has made progress in the implementation of Environmental Management System and had planned to get the certification by March- 2003. However, with the current directives of Finance the progress has stalled, as tender cases for certification have been pended for want of finance vetting.

i) Environmental policy and procedure manual have been issued.

ii) Acceptance letters have been issued to M/s R.S. Certification (P) ltd.-Vadodra for certification and M/s ICL Certification Ltd.-Punchkula-Haryana for educational training on 18.03.06.

iii) Instruments required for monitoring environmental parameters have been received except incubator and PH meter.

iv) Two important requirements to comply with state pollution norms are effluent treatment plant and incinerator. The progress is as under :

 a) Incinerator : 

The work was awarded to M/s B.L. Engineering-Ahemdabad on 19.09.2005.  Installation & erection has been completed. Water & electrical connection have been

 provided. Firm has been advised on 24.04.06 to arrange for trial as per RSPCB? norms and also comply to    the discrepancies noticed.

 b) Effluent Treatment Plant : 

The Work was awarded to M/s Environmental Engineering-Indore on    29.10.05 commenced on 20.01.06. The work of ETP is at completion stage. Electrical connections are being provided to take trail to run the equipments of ETP.

  c). BIO-DIESEL.

 A humble beginning was made by planting 5 Jatropha trees near line No.16 in June-05.  100 Jatropha  plants in this month and total 325 plants have been planted up to March-06 in various locations of  workshop. 

In the works programme proposed for improvement in the circulating area of workshop, 1.2 Hectare area has been kept for plantation of Jatropha trees.

 

Important mile stone in the implementation of ISO- 14001:

       

 S.no

Activity

Responsibility

Target

Present status as   
  on  25/05/06

1.       

Issue of Environmental Policy

ISO-CELL

31/05/06

 

2.       

Training & Awareness of ISO-14001 & Environmental Policy of all staff (in House training)

DyCME(R)

SSE/BTC

15/06/06

 

3.       

Shop wise identification of environmental aspects of each activity

SSE/Concerned

15/06/06

 

4.       

Training for Internal Environmental auditing for supervisors by external agency

SSE (PRG)

27/05/06

Out of 45 Supervisors 30 has been trained

5.       

Training for lead assessor for officers by external agency

SSE/PRG

20/05/06

Completed

6.       

Training for safety & emergency preparedness & response of workers & supervisors (in house & out side at Jaipur)

DyCME (R)

AWM (G)

Completed

59 Supervisors are trained at JP

47 has been trained in First Aid

7.       

Apply for yearly consent to operate with prescribed fee under Air, Water & Hazardous waste management Act.  to RPCB (State Pollution control Board)

AWM (G)

CMS-I/LAB

15/06/06

Being Followed

8.       

Pollutant measuring instruments

SSE-PRG

30/06/06

Purchasing of Incubator is under process

9.       

Preparation & Issue of documents ? Level I

ISO-Cell

31/06/06

Document Under preparation

10.   

Preparation & Issue of documents - Level II (Procedures)

ISO-Cell

30/06/06

Document Under preparation

11.   

Preparation & Issue of documents - Level III & IV (WI?s)

ISO-Cell

30/06/06

Document Under preparation

12.   

Documentation review by Certifying Agency

MR

15/07/06

 

13.   

Compliance of document Review

MR

30/07/06

 

14.   

Ist Internal Quality Audit

ISO-Cell

04/08/06

 

15.   

Compliance of NCR?s & Observations of IEA

SSE/Concerned

19/08/06

 

16.   

MRM

ISO-Cell

22/08/06

 

17.   

Pre-assessment audit by Certifying Agency

MR

30/08/06

 

18.   

Compliances of Pre-assessment audit

MR

09/09/06

 

19.   

Certification audit by Certifying Agency

MR

15/09/06

 

       

 